ME21N
account assignment : P Project, Item category D, PO with material group P001 services
Item line 10: service n° introduced, WBS element introduced
and screen asks for G/L account and WBS element for line 20, then 30...
Changing screen to push "repeat account assignment off" but still ask for G/L account and WBS element for line 50...