S/4 -> PP/DS: Prohibit rescheduling in PP/DS after changing Dates in S/4HANA 1809

651 Views

Hi guys,

in our business case we want to use embedded PP/DS for scheduling planned orders for our inhouse production.

After conversion to production order, we transfer them to an external MES which is executing a detailed scheduling.
We use Z-IDOC for writing back the new dates and times into the production order.

As described in SAP NOTE 684356 (https://launchpad.support.sap.com/#/notes/684356/E) it´s not provided in standard system to accept the new dates in SAP APO; PP/DS without start rescheduling. But that is exactly what we need to ensure consistent capacity requirements in PP/DS.

We tried some enhancements (https://help.sap.com/viewer/f899ce30af9044299d573ea30b533f1c/1809.002/de-DE/7939c95360267614e10000000a174cb4.html) for inbound and outbound processing.

Unfortunatly we found no solution until now.

Do you have any ideas or helpful information for our issue?

kind regards
Sebastian