Hello,
I have a situation where for a particular material I have 1 order from last month with 20 units that is not yet confirmed since there is 0 units in stock. Today I had a planned order with 20 units for same material and plant, in CO09 it shows this with MRP element for planned order, rec/reqd qty is 20 and cumulative ATP qty is 20 for this MRP element. But in CO09 the cumulative ATP qty for stock on today's date is still 0 for this material and plant.
Shouldn't the 20 units that I am receiving from Planned order be added to the stock cumulative ATP qty? Or is it that because I have a order with 20 units waiting so the net ATP qty is 0? But that doesn't make sense since that order is still not confirmed.
In my scope of check, Incl. planned orders is marked as X and Check without RLT is blank.