Capable to Promise for Configurable Order as MTO

192 Views

Hello Experts

Need help in CTP fr configurable Sales order as MTO , i tried to set up the CTP with PPDS and getting below issues

1. The Requirement Date from sales order is not Passing to PPDS to plan the supply, as whenever i changed the requested date for the order , the system always plan on particular date June 15,2020 even i changed the requested date to June 20, 2020.

2. When i saved the sales order Planned order generates with incorrect scheduling dates on June15,2020 though capacity is available before this date even , always plan on this date and tried to schedule to before this date but couldn't allow.

3 Also the Planning Log button not showing any result.

i have used planning Procedure as 3 for finished and 1st layer of component as well , as 1st level of component is also MTO material, and setting in Check instruction is used as Production Directly and not using any method of ATP check since it is MTO order.

Kindly let me know what i am missing to configure the correct scheduling in CTP with PPDS