In ATP check, we can check Purchase Orders/VSA. The system will use the schedule date from table EKET. This date takes into account the GR time defined in the material master record. For instance, scheduled date will be 2/6/2020 but available date in MD04 will be 8/6/2020 because we defined 6 days GR time.
In ATP scope, we crossed the flag "No RLT".
ATP check uses the scheduled date to confirm our planned orders but we want that system uses Scheduled date + GR time. This is for us some security about components availability.
Is there a way to work that way?
Br,
Chauvenne JM