SAP MM Release Strategy

110 Views

Hello ,

I have setup a 3 level release strategy for PO release . With 3 different value slab. I create a PO with 50 qty , 2 levels trigger based on values and then I release the PO .

now I go back to the PO and reduce the qty to 45 , since the value is still in the same slab the release strategy will not reset . I would want to know the process to define so that any minor reduction should reset the strategy . Can anyone please help.