We have ALCM (Asset Life cycle management) project running at the moment and go live will be 1st of September 2020. Some maintenance plans are already running like 3M, 6M and 12M in Single cycle.
We are moving to Strategy Base plan.
My question:- is there any way,we can set start data of plan at operation level.
If we will give start data as 15.09.2020, the 3M will start from 15.12.2020, But others like 6M and 12M will start from 15.03.2021 and 15.09.2021 respectively
In AS IS situation, we have all 3M,6M and 12M is schedule in Dec 2020
in TO BE, We want to schedule it in such a way that 6M and 12M also starts in Dec 2020.
I cannot see any Off set field for operation.
Your early response will be much appriciated.
Thanks
Sudip