Hi community!
we have the following case;
- Parent 1 BoM includes child 1
- Parent 2 BoM includes Parent1, Child2
- Parent 3 BoM includes Parent 1, Labour
when producing Parent3 using Production Order type "Production" how we can produce the Parent2 and its content as well?
by default, SAP B1 allow just the production of the Parent2 without producing the Parent1, this case is sometimes required not all the time to skip the intermediate Parent1 BoM.
MRP is not fitting the request, because as long as there's balance of one of these items in the warehouse, it's not providing the ability to produce it accordingly with the parent item,
All what we need is; when we produce the Parent item, automatically all the subitems get produced without manuall intersection,