mts-problem.jpg
Dear SAP PP Community,
WHAT I DID
1. MM01 MATERIAL MASTER CREATION STRATEGY TYPE 10
2. MD61 REQUIREMENT GENERATED IN IT FOR 3 MONTH 300,200,200
3. MD02 MRP RUN
4. MD04 STOCK REQUIREMENT LIST I CAN SEE THE PLANNED ORDER
4. CONVERTED PLANNED ORDER INTO PRODUCTION ORDER AND RELEASE THE PRODUCTION ORDER
5. CO15 CONFIRMED THE PRODUCTION ORDER
6. CO02 TECO THE PRODUCTION ORDER WHAT I SEE AT LAST.
7. REQUIREMENT NOT VANISH AS ALWAYS, WHY, WHAT IS THE SOLUTION?
THANKS AND REGARDS IN ADVANCE