How to mass update same task list operations, that are used in several task lists?

641 Views Last edit May 26, 2020 at 07:47 PM 2 rev

Hello SAP experts,

in our company we want to create several task lists, that contains sometimes same operations. If we change one of these operations we would like to have the change in all task lists. Is it possible to link these operations or to add them as a reference to a global operation?