cancel
Showing results for 
Search instead for 
Did you mean: 

container handling

former_member563943
Participant
0 Kudos

Hi All,

i have below requirement,

Finished Goods - M151 is stored in a container , with the current Z Transaction the Container is upfront created , both as bin in physical warehouse and a material in the logical warehouse . The Storage type and bin in the logical warehouse represent the position of the container in the Crane yard. Movements & Status changes of the container as well as reports are all own developed

Plant Sloc WH S.Type Bin Material Physical Warehouse 6100 1500 150 015 2064 M151 Logical Warehouse 6100 1599 159 003 V213 2064

I guess the below can be sufficed with Handling unit, but how to go about it , please share details to prepare the process flow on this .

Regards,

Preeti.SS

Accepted Solutions (0)

Answers (0)