Need to plan material correctly as per delivery date in MRP

99 Views Last edit May 20, 2020 at 07:13 AM 2 rev

Hello Gurus,

We have a process as given below-

Plant A-->Plant B ( we send semi-finished product)

Plant B-->Plant C we send final product (Scheduling agreement is created)

Plant C--> directly to client we send finished product AFTER repacking

Current Settings per plant wise given below-

Plant A- PDT time 7 Days

Plant B- PDT time 7 Days

Plant C- PDT time 12 Days along with Safety time ind. 2, Safety time/act.cov. 5 days

Now the requirement is

We need to deliver parts to PLANT C at least 12 days earlier than customer delivery date, Hence they could repack the parts on time and send them to customer.,

So if on PLANT C there is the customer order for example for 200 pcs on delivery date 14/MAY, they should receive the parts from PLANT B at the latest on 03/MAY.

so planners from Plant B needs to be assure that the parts to be ready at PLANT B 26/APRIL"

Kindly Suggest what settings should we need to maintain to achieve this.Now the parts are received late from plant B to Plant C.

Thanks in advance.

Regards,

Sandeep