May 19, 2020 at 02:48 PM

How to automatically change a Production order after a change in the external subcontracting PO ?

85 Views

Hello Community,

We currently have a issue in our external subcontracting process.

Indeed, when we need to change the PO by deleting the item 0010 and adding a new line, the production order is not updated with the new information.

We usually work with materials without reference and therefore add the components through the "components" button in the line master data tab.

Is there any way these changes can be automatically transferred to the production order for an update ?

Thank you in advance for your help.