Individual wave calendar is not take into account

1454 Views

Hello EWM experts


I have a standard calendar for my warehouse with 5 working days (mo - fr). Additional I have a second one with 7 working days including holidays.

In my wave template I used my second calendar (mo - su) and it is found during wave assignment, but weekend is still ignored and the wave is created for Monday.

Thanks for help!