Using a material with serial number in bom

0 Kudos

Hi all,

We want to add a new product and need to use the one we have already produce(has serial number) in a different one. For Example;

1000xxx - the one we produce and sell(has serial number)

1000yyy- the new one that we use three of 1000xxx (also must have serial number)

After i create bom in cs01 and plan in ca01, try to open a production order in co01 and try to put check in Indicator specifying that the material component is backflushed on the line 1000xxx material and save, system errors.

Hope i can explain.

Thanks for your support.

Accepted Solutions (0)

Answers (2)

Answers (2)

Ritz
Active Contributor
0 Kudos

melrajas,,

is it correct if i say , while doing production order confirmation you are getting error. You have a serialize Assembly 1000YYY of which you want to consume 3 pieces while producing 1000XXX.

1) what settings you have for material 1000YYY , as you need to assign specific serial numbers from stock of 1000YYY. Have you created Ibase ? once you create an serial number at header level, create ibase using IB51 and maintain all the components and their serial numbers in IBASE.

https://help.sap.com/doc/saphelp_sm71_sp13/7.1.13/en-US/b9/d3ad54b4eff657e10000000a423f68/content.ht...

2) Also please share the exact error message you are getting .

Please also go through below few links it will help you with basics of serialization.

https://blogs.sap.com/2015/07/29/serialization-process-and-options/

Thanks

RD

Ritz
Active Contributor
0 Kudos

melrajas,

Could you please describe it again , do you mean you want to change the serail number range for your product from 1000XXX to 1000YYY ?

Thanks

RD