PR delivery date is far in the future through MD02

51 Views

Hello All,

This may be repetitive issue for you, but I went through no of threads but did not get what I want.

So opening this new thread.

Material master settings:

GR processing time 1 day

planned delivery time 14 days

Tot. repl. lead time: 40 days

Pur processing time: 1 day OPPQ

transit time: 5 days

Now PR creation date is 18.03.2020

PR delivery date is 16.06.2020

PR is created through MRP. Can you please let me know what is causing this delay in delivery date calculation?