Whenever i am creating an order in IW31 and filling the materials in the components tab it is asking me to enter the unloading point ad goods recipient value in the respective fields, what are these fields used for and what is the significance. Also have noticed that some of orders that have been generated though maintenance plan scheduling already have the values in the unloading point & recipient field. What am i missing ?

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    Posted on May 10 at 08:55 AM

    Hi Mahanty,

    There are multiple ways to populate it.

    1. Through user exit

    2. User default - Click Extras - Settings - Default Values - External Processing Tab and External Procurement Tab

    3. If Maintained in the Task List, when scheduling it will be populated here.

    Regards

    Terence

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on May 07 at 09:54 AM

    Hi,

    Unloading Point - The unloading point represents the address at which bundles of issues are loaded or unloaded for delivery using a vehicle

    Good Recipient - Specifies the recipient for whom the material or the service is destined.

    You can use F1 in the field, to understand the purpose of it.

    Secondly, if it is auto filled, check the Task list assigned to the Maintenance Item for the Maintenance Plan, actually it was coming from there.

    Regards

    Terence

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on May 08 at 07:13 AM

    Sthitapragnya Mahanty

    Typically speaking, the unloading point and goods recipient are not mandatory fields in PM/CS orders.

    The will be some MM config that makes these fields mandatory.

    .

    PeteA

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on May 08 at 07:55 AM

    Hi Mahanty,

    Check the Operations and component details, check the External Tab, see whether any details are maintained.

    Regards

    Terence

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.