Hi,

How can we delete the remaining plan cost in Easy Cost Planning through a Program? I want to delete the remaining plan cost in the project before the status is set to CLSD. I could not find any BAPI or FM to delete the ECP cost at WBS level.


Thanks,

Srin.

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Posted on May 12 at 05:24 PM

    Hi,

    You can use CNECP_READ FM to read the ECP data of WBS and delete them.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on May 12 at 06:47 PM

    Thank You Akash. Does this FM reads all L5 WBS ? We have ECP cost planned to all L5( which are Lowest level) or Can I call CNECP-READFM and pick L1 where PRPS-STUFE=1 and delete the rolled up cost at L1.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.