Hi All,

There is a requirement to perform budget check in S4 against a PO/ PR in Ariba through CIG. I am looking for steps for the s4 side configurations required to set up this interface.

And if we need to show a custom message to user in Ariba in case the budget check fails in S4, how can we do it?

Thanks,

Ruchi

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on May 12 at 02:07 PM

    Hi Ruchi,

    Please find the below for references, hope it will be helpful..

    Overview of budget check functionality, once the budget-check feature is enable in Ariba buying and invoicing solution.

    • Buyers create a purchase requisition for products and services in procurement application
    • Prior creating the requisition in S/4, it allows user to check budget availability for requisition
    • Based on the check status initiated, requisition is approved and then get converted to Purchase order
    • On approval fund/budget are reserved for requisition
    • if the validations w.r.t accounting information and budget availability fails in backend
    • Failure message will be sent Ariba Procurement solution, same can be viewed under history tab of the requisition
    • Then the status of requisition is changed to composing.

    Steps to configure real time budget check in S/4 On-Premise/SAP ERP

    Pre-requisite

    • Document type and end point should be maintain in CIG
    • Run the interface setup program in S/4/ SAP ERP for SAP Ariba Procurement
    • Give all the required details such data center, connection instances, log in details etc
    • Then select the requisition export request checkbox under inbound message send from SAP Ariba Cloud Integration Gateway
    • On completion of above steps, initiate the requisition in Ariba Procurement against internal order or WBS where budget profile is configured in S/4/SAP ERP and click on check button.
    • Triggers the budget check request to S/4/SAP EPR.

    And if we need to show a custom message to user in Ariba in case the budget check fails in S4, how can we do it? [There is a standard BADI provided for manipulate the data as per customer requirement, The post-processing method can be used to display the customised message]

    Regards,

    Niraj Nirola

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.