Hi all,

We are on Standard ECC (No PP/DS) and have a question regarding the automatical reduction of floats for production orders.

what we want to achieve:

System should reduce the floats in production orders but not reduce the queue times of operations.

what we did:

we have defined in OPU3 reduction levels and percentages to reduce the float. We defined 5 elvels and opted for " Do not reduce beyond level 5". In OPL8 we have a reduction startegy that does not touch the queue time, does no split of transport tiem reduction. We use scheduling margin keys to set the floats. All fine.

The issue we have:

When scheduling an order the system set a reduction level but does not reduce the float times. It stays the same.

Any idea of what we missed out is greatly appreciated.

Anne Mielke