Dear Experts,

Question 1:

I want to make start date and time as a defaulted with system date and time and based on that RFx end date and commercial open date and time is to be calculated and to be shown in read only mode as Start Date and time + X no.of days while creating my RFx in SAP SRM 7.02.

Question 2:

I have configured some custom fields and I want to hard code values based on values entered and some fields to be defaulted with hard code values and to be shown while creating my RFx in SAP SRM 7.02.

Regards,

Ramesh.

Accepted Solutions (0)

Answers (1)

Answers (1)

laurent_burtaire
Active Contributor

Hello Ramesh,

Question 1:

use an implementation of methode BBP_BID_CHANGE for BAdI BBP_DOC_CHANGE_BADI.

For the read-only functionality, use metadata.

Question 2:

Use same BAdI implemention as question 1.

Regards.