on 05-02-2020 8:27 AM
Dear all,
while work order confirmation in IW42 user enter wrong actual finishing dates .(instead of 30.04.2020 he entered 01.05.2020) so now in order actual finish date updated wrong, then user cancel confirmation in (IW45). again confirmed the same order in iw42 .but in work order dates not updating. i tried in development but dates are updating what went wrong. could you please explain
Dear Peter,
We didn't,reschedule the order. but again we cancel in IW41 this time, i dont no but actual finish date updated.