Hello Community,
I have a doubt regarding SAP IBP Process Management.
A Process Template has 3 steps.
Setting for Automatic Start of Step 2 and 3 is "When all tasks of previous steps are completed"
Now, if the task of step 1 is completed in 2 days and the task is marked as completed in SAP JAM, will the Step 2 be triggered?
Basically will it override the duration setting? And not wait till 5 days to start step 2