on 04-24-2020 6:07 PM
Phase/operation in process order 70001002 does not exist (please check entry)
Hello
In transaction COR6N you will post a Phase confirmation, therefore, you need to provide the order number and the phase number together.
In transaction CORK, you will be performing an order header confirmation, so you will be confirming all the phases under this order, therefore, you don't need to provide the phase number.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello
You do not create a phase number, they are automatically created wen you create a process order and you can the phase numbers in COR2 (usually they will be 0010, 0020... ). When using COR6N you will have to post confirmations for each one of the order operations.
Regards,
Caetano
Hi,
Please explain the issue in detail.
Based on the above statement make sure that process order created with Master Recipe operation/phase details.
Best Regards,
Lingaiah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.