PP/DS - Procurement from alternative location w. atp check

matteo_bongiorno
Participant
0 Kudos

Hello all,

i have two trasportation lane, one for another location (plant) for intercompany procurement, second one for purchasing from vendor. The first one have priority. It is possible during purchase requisition creation during mrp run, assign the first TL only if there is enough available stock in the intercompany plant? Otherwise, switch to second TL for purchasing?

Thanks in advance.

BR

Accepted Solutions (0)

Answers (1)

Answers (1)

matteo_bongiorno
Participant
0 Kudos

i forgot: pp/ds is the new embedded solution in S/4 hana. i do not think RBA is still available. thanks.