on 04-01-2020 4:48 PM
Hi,
We are trying to create PP confirmation with auto GR to embedded EWM storage location. But confirmation stucks in CO1P.
If we change to IM storage location, confirmation and GR document is being created. Or if we do the Production Order GR with MIGO seperately, again inbound delivery is being created.
But when we do the auto GR with confirmation, it stucks in CO1P (without any message).
Is there any suggestions?
Regards,
The ERP-EWM integration customizing were wrong. When we corrected that customizing, CO1P started to run properly.
Also we had another reason; Somehow adress number of the plant does not exist in the QA system. Means, T001W-ADRNR of the related plant does not exist in ADRC table. That also caused same issue for auto GR via confirmation.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.