Dependent requirements FOR SFG are getting preponed than the FG planned order

kraghavanbindhu
Contributor
0 Kudos

Planned order created on 01 .04 .2020 for FG

But the Dependent requiremetns are creaed in 31.03.2020

Why the requirements are passed to previous day

Accepted Solutions (0)

Answers (1)

Answers (1)

kumar_semmalai
Contributor

Hello

Planned order created on 01 .04 .2020 for FG -

its not a Planned order creation date. its a FG Stock available Date in the warehouse.

In your case, Might be your FG production time lead time might be 1 day, That means , your Planned order Opening date will be 31/03/2020. So, the SFG requirement Date also 31/03/2020.

Regards - Kumar Semmalai

kraghavanbindhu
Contributor
0 Kudos

We are not using any opening period. The schedule margin key is 000

kumar_semmalai
Contributor
0 Kudos

Can you share your Planned order screen. ?