Dependent requirements FOR SFG are getting preponed than the FG planned order

Planned order created on 01 .04 .2020 for FG

But the Dependent requiremetns are creaed in 31.03.2020

Why the requirements are passed to previous day

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Mar 25 at 11:19 AM

    Hello

    Planned order created on 01 .04 .2020 for FG -

    its not a Planned order creation date. its a FG Stock available Date in the warehouse.

    In your case, Might be your FG production time lead time might be 1 day, That means , your Planned order Opening date will be 31/03/2020. So, the SFG requirement Date also 31/03/2020.

    Regards - Kumar Semmalai

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.