1. Create / release your production order

2. Pick/Transfer raw goods

3. Post goods issue

4. Partial confirmation of Production Order

5. Calculate WIP

6. Run Settlement

7. Confirm remaining production order

8. TECO

9. Calculate overhead

10. Calculate WIP

11. Calculate Variance

12. Run Settlement