I have a real issue; I set up 2 release strategies S1 and S2.

Here are the characteristic values for S1

  • Account Assignment Category: Cost center
  • Cost Center: 02-2155
  • Creation Indicator: Realtime (manual)
  • Total value: 0.00 – 2499.99 USD
  • Plant: P2, P3 and P4
  • G/L Account Number: 0000500300
  • Material group : 72000000
  • Purchase requisition Document: NB

Here are the characteristic values for S2

  • Account Assignment Category : Cost center
  • Cost Center: 02-2155
  • Creation Indicator: Realtime (manual)
  • Total value: >= 2500.00 USD
  • Plant: P2, P3 and P4
  • G/L Account Number: 0000500300
  • Material group : 72000000
  • Purchase requisition Document: NB

S1 and S2 are item level release strategies.

As you can see the only difference between S1 and S2 is the total value

When I create a purchase requisition with a value of 1000 USD, release strategy S1 kicks off

When I create a purchase requisition with a value of 3000 USD release strategy S1 still kicks off

But when I change S1 and S2 to header level, S1 kicks off for a purchase requisition of 1000 USD and S2 kicks off for a purchase requisition of 3000 USD.

But at item level, S2 never kicks off, only S1 kicks off.

Please have you seen a similar issue?

Thank You.

Accepted Solutions (1)

Accepted Solutions (1)

JL23
Active Contributor
0 Kudos

I am pretty certain that you are using the wrong value field from the CEBAN structure

GFWRT is for overall release strategy

GSWRT is for item release strategy

Answers (1)

Answers (1)

former_member259132
Participant
0 Kudos

Thank You very much Jurgen, You were right, I changed GFWRT to GSWRT and it is now working.