Hi SAP Experts,

I have a very common requirement where my client want a report to see cost estimate breakup (BOM, activity price and Overheads) for multiple materials. I believe this is a very common requirement but I don’t think so there is any standard t-code given by SAP for such.

I have checked various threads regarding this and as per threads below BAPI I need to use to develop the report. But I am not able to understand how to use those BAPI. If anyone has developed this kind of report kindly help me with logic I need to give to my developer.

BAPI_COSTESTIMATE_GETLIST: Determine cost estimate lists

BAPI_COSTESTIMATE_GETDETAIL: Determine detailed information for a cost estimate

BAPI_COSTESTIMATE_ITEMIZATION: Determine itemization for a cost estimate

BAPI_COSTESTIMATE_GETEXPLOSION: Determine BOM explosion for a cost estimate

Execute BAPI_COSTESTIMATE_GETLIST first to get the list of cost estimates.

Will appreciate your reply. Please help.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Mar 13 at 06:24 PM

    Closing the issue as resolved it myself.

    Solution - I have used Function module - CK_F_CSTG_STRUCTURE_EXPLOSION.