HI Experts,

Right now are doing the IBP to BW integration via CPI DS. But i just wanted to know are there any other possible ways that we can directly send data from IBP to BW.

Please let me know your coments here.

Accepted Solutions (1)

Accepted Solutions (1)

former_member194529
Active Contributor
0 Kudos

Hi Satish,

If you want to provide an Improvement Request on this regard, please refer to:

2479068 - IBP: How to provide enhancement / improvement requests or feedback for Integrated Business Planning product

https://launchpad.support.sap.com/#/notes/2479068

AnjuK
Discoverer
0 Kudos

Hi Ivan,

I am looking for a document that can help me with the info on IBP integration with BW4HANA as I need to send IBP data to BW to be used in reporting. Please let me know the relevant resources for this. Thank you.

Kind Regards,

Anju

Answers (2)

Answers (2)

balazsbence95
Active Participant
0 Kudos

Hi Satish,

As per PAM, you can load data from IBP to BW by using native BW target datastore. Page 6.
Here you can see the IBP templates available that you can use:
SAP Help Portal - Templates for SAP Integrated Business Planning for Supply Chain

Best regards,
Bence

riyazahmed_ca2
Contributor
0 Kudos

Hi Satish,

It is not possible. We have to use CPI-DS only to integrate IBP with any system including ECC, S4HANA, BI/BW with or without HANA. SDI is a different topic all alone. Refer the below link for more details.

https://help.sap.com/viewer/da797ae2bf6246d58abd417f24915d55/2002/en-US

Regards,

Riyaz

AnjuK
Discoverer
0 Kudos

Hi Riyaz,

I have a similar requirement of sending IBP data to BW4HANA. Somehow the link you provided is not working. Do you have a working link I can refer to for more details please?

Kind Regards,

Anju

riyazahmed_ca2
Contributor
0 Kudos

Hi Anju,

In IBP, apart from normal CPI-DS based Integration, we have several communication scenarios to send the data to/from IBP.

CPI-DS based integration needs the definition of data source, data target. We can even load the data into PSA/cube directly by using the CPI-DS. This is my fore-most suggestion.

Othewise, we can use communication scenario named SAP_COM_0720. This is an odata based configuration in IBP. Once the communication arrangement is ready, you can collect the odata link from the IBP configuration and pass on your own query in SQL format.

Refer the helper links below.

https://help.sap.com/docs/SAP_INTEGRATED_BUSINESS_PLANNING/feae3cea3cc549aaa9d9de7d363a83e6/f675b55e...

https://help.sap.com/docs/SAP_INTEGRATED_BUSINESS_PLANNING/da797ae2bf6246d58abd417f24915d55/89e5e24a...

Let me know for any help.

Thanks,

'Riyaz'