MRP not generating proposals for dependent requirements

345 Views

md05.pngmd04.png

mm03.png

Hello Experts,

I am facing an issue where MRP is not generating proposals (Planned orders) for a packaging material. Dependent requirement for future is available for the material. This packaging material is having scheduling agreement. While executing MRP for this material, a standard error occurred and which mentioned as “Maximum no. of order proposals per deadline exceeded”. Number of proposals maintained in plant parameters are 100. Planning calendar is used as PK (Friday). Minimum lot size is 0 and rounding value also set as 0. I have also searched for relevant threads throughout google, unfortunately, I don’t want to change configuration since this issue is happening for only a single material. Attached screenshot for MM03, MD04 and MD05. Material also have open contract.

Please suggest.

Thanks in advance.