SAP PM WORK CENTER CAPACITY

rsk_gsk
Participant

Dear all,

From plant maintenance point of view how to define work center capacities and how it will impact when we assign SYS. condition's. as 'o'. will this stop to release process order/ production order in PP, can you give steps to so i can prepare a demo for this like PM-PP integration.

rsk.

Accepted Solutions (0)

Answers (2)

Answers (2)

lingaiahvanam
Active Contributor

Hi,

You can follow the below steps.

1. Maintain production Work Center in Equipment -> Location Tab -> Work Center.

2. While creating breakdown maintenance order select system condition should be "0" not in operation. After selecting work Center capacity consumed against the Maintenance order.

3. Activate the 'Capacity check' in the production planning order dependent parameters, you have to create a capacity requirement planning profile and assign it to the production order type.

4. Run capacity planning in CM25 you can see the work order with consumed capacity information.

Best Regards,

Lingaiah

i520
Advisor
Advisor
0 Kudos

Hello,

Please check the recent thread below, I put screenshots in my response.

https://answers.sap.com/questions/12966050/capacity-block-in-case-of-maintenance-order.html

Regards.

Farid.

rsk_gsk
Participant
0 Kudos

Thanks,

Farid Azzi and lingaiah vanam its help me lot.

Rsk.