Dear Experts,
I'm testing the SOP flow, IN S/4 but I can't get the RCCP to work in MC81 transacation.... in any way!
Current Settings:
1) I've activated the SOP for the Plant
2) OPU4 with both active flags. Here i try before SelID : 03, and then SelID : 01 because routing of the materials are N type.
3) LTP flag active in Work Center Capacity
So I created a product group in MC84 with 2 materials : SOP1 e SOP2, both materials have the production versions checked and verified.
I create in MC35 RCCP Profile as you can see in the screen.
When i check RCP in MC81 I have message MA300.
In Capacity-Work Center I use the standard Processing Formula SAP006, if I try to schedule a Planned Order, Capacity Requirement it's ok.
I mantain lotsize in routing as in production versions.
Does anyone have any idea what's missing?
Thank you!