Skip to Content
2
Jan 23, 2020 at 10:44 PM

Production order for alternativ workcenter

84 Views

We are running a setup with a MES on top of MII, where it is possible to run on an alternative workcenter, than original planning from ECC side. We are now working to spread out the use of MII OEE, and here we have not found a way, where we can activate the production order on an alternative workcenter, which is not part of the LOIPRO from ECC.

Is there anyone which have tried to get the MII OEE to accept to activate the production order on an alternative workcenter, which was not planned, so we can report production via this alternative workcenter incl. waste, downtime, etc.?