Hi Team,

We have a situation like, we not issued like XYZ material, even stock not available.

We can make entries, to receive / Goods receipt XYZ material with Batch from Internal order / subcontractor using movement type 262.

Now the question

Batch created while goods receipt but some batch information is missing like Date of Manufacture & SLED fields are empty.

Is anything missed or wrong?

Thanks in advance

Sankaran

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

Movement 262 is a cancellation of the goods issue for an order reservation and it should not be used for a goods receipt.

If you check this material movement settings in the customizing transaction OMJJ you will observe that the flag Check SLExpir.date is not checked, so the Date of Manufacture and SLED won't be checked when this movement is posted. I would not change this setting, as it might cause some side-effects when you are actually posting a reservation cancellation.

I suggest you to try movement 101, that is an actual goods receipt movement.

Regards,
Caetano