Hi
I want to synchronize the Status for the following Scenario
1) Item - PS Project Definition
a) PS Project is created automatically created with the Lock Status and I want to Unlock the Project Definition based on the change of certain status in Item to the Project definition in PS
b) If the Item Status is Hold then the linked Project Definition Status should be Locked
2) Decision Pont - WBS
a) The linked WBS to Decision Point needs to be Released ("REL" Status) when there is a certain change in Status in the Decision Point
b) If the Decision Point Status is Hold then the linked WBS Status should be Locked
3) WBS - Decision Point
a) Change in Status of WBS for eg. TECO/CLSD there should be a certain change in Status in the linked Decision Point
4) Decision Point - Item or Item - Decision Point
a) Change in Status of Item should trigger the change in Status in Decision Point and similarly change in certain status in Decision Point will trigger the change in status in Item
In the setting SAP Portfolio and Project Management > Common Functions > Decision Flow Management Settings > Attribute Synchronization > Maintain Field Mappings you cannot map the Decision Point Status to WBS Status
Thanks and Regards