Dear Experts,

In J1IGSUBREP report, "material document wise recon. details" tab, date range is on challan date which is required on material document posting date. Is there any other option / tab to run this report on material document posting date?

Running this report on material document posting date will help us to file return ITC04.

Regards,

T P Nautiyal

Accepted Solutions (0)

Answers (1)

Answers (1)

Lakshmipathi
Active Contributor
0 Kudos

Check whether you need to carry out manual activities as recommended in OSS note 2697672

0 Kudos

Hello sir,

I am trying this tcode J1igsubrep.. But the system is throwing error doesn't exist. Is there any note or some how activate this.. If not can you please suggest a report for job work challan reconciliation.