on 12-26-2019 1:23 PM
Dear Team,
I have a Scenario where:
There are 5 service masters and each service master has a different price which is defined in ML45.
I need to configure the Release Strategy (Block PO when the price increases from the condition) with respect to the service master record price.
Note: I do not need the Release Strategy for the whole document value, I need it with respect to the service master and its price. Please let me know the possible configuration.
Regards
Vignesh Shankar Raj
Standard SAP does not support release strategy at item level for PO. Following link will clarify it better:
https://answers.sap.com/questions/6858071/release-strategy-at-item-level-in-po.html
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Pulin Bhatt,
There will be only one line item in the PO as per the business. i.e, only one service master is called for one Service PO.
Let me explain the details:
For example,
Service Master 01: Price 200 INR maintained in the condition
Service Master 02: Price 500 INR maintained in the condition
We have maintained class and char with respect to Plant, Doc Type.
In-Service PO,
We enter the Service master in the service tab (Service master 01 with 200 INR is fetched), if the user changes the price >200 USD, it has to trigger a release strategy.
The same for Service master 02, if the price is increased >500 INR
Is there any possibility to have this combination of characteristics in the release strategy: Doc Type, Plant, Service master, and its value
Regards
Vignesh Shankar Raj