Good afternoon!

The task is next: load Inspection Plan in the system with the help of Migration Cockpit instrument. Use Incomplete copy model for MIC transfer.

At the end of the process I noticed completed field "Target value" with zeroes despite the fact that the indicator "Indicator for Check Target Value" was not set.


With what it can be connected? And how can this be fixed?

Ksenia, with regards

Attachments

untitled.png (38.2 kB)