We are running bottom up heuristics after the PP DS heuristics to reschedule orders based on priorities. The priorities defined are Requirement Date/time and Order Priority.
The issue happens that though there are available capacity and material for the component but still the bottom up reschedules few orders to a future date. We have the setting to reschedule only in future set.
How can i investigate why this is happening. Can anyone throw some light.