Labor cost

former_member627545
Participant
0 Kudos

Hi, all. I want to know about assignment labor cost. I know that payroll system is not working in ByD. So how can i distribute direct labor cost and in direct to materials or cost center? I don't know actural wage and how i can assign...

Thanks regards,

Dasom

Accepted Solutions (0)

Answers (4)

Answers (4)

former_member624513
Active Participant

Hi Dasom,

As per your question, I believe you want to know how to assign the labor resources to the cost center (correct me if I am wrong)

Labor resources are employees or groups of employees with the same skills and qualifications with the capability to perform specific project tasks.

Please follow the steps below to create a resource with a combination of assigned Job role and employee assigned Cost Center.

  • Go to the Cost and Revenue work center.
  • Select the Master Data view > Resource subview.
  • Select the New button > Labor Resource.
  • Enter the current cost center assigned to the employee XYZ i.e. Cost Center ID and Job ID to which employee belongs to.
  • Fill in other fields as shown in the picture and select the Save and Close.
  • The newly created Labor Resource should appear in the list. Select and choose the Edit button.
  • In the Valuation tab, you can adjust the settings such as Cost Center Assignments, Maintain Cost Rate and Job Assignment as needed.
    (The Cost Rate can only be maintained after activation of the resource; this cost rate overrides the service cost rate in service cost allocations and project cost estimations.)

Valuation :

Please note:

  • If you have more than one labor resource for the same cost center & validity period, you must have a unique job assignment for each labor resource.
  • The unit of currency for the cost rate has defaulted from the cost center’s company.
  • Employee must have active Labor Resources from a day earlier than the time recorded date.

Let me know if it helps to answer your question.

Regards,

Priyanka

former_member627545
Participant
0 Kudos

Hi Priyanka,

first of all, i really appreciate your kindness. It is really helpful to me. Sorry but, can i have some additional question?


1. As your answer, i have a question what affection there are between job assignment and labor cost allocation?

For example, if there are 3 employee in "production worker", production worker cost rate is allocated at a production lot when i choose which one of these employees?

2. What relationship are there between cost rate of Labor Resource and Actual cost?
Which criteria can be referenced for clearing this balance?

3. Actually, i want to know influence of actual payroll(or wage) into actural lobor cost. Could you update on me?


Best regards,
Dasom

claus_tropitzsch14
Discoverer
0 Kudos

Hi,

I tried to set up the Service Cost Allocation to projects but I can't get any cost allocated to projects by entering hours in time sheets. I set it up as follows:

1. Created a new account determination group.

2. Created a new resource and entered cost rates for each set of books.

3. Created a new service and also created cost rates for each set of books and assigned the newly created account determination group to this service.

4 Assigned the test user of the time sheet by his role to the resource.

5. Assigned the user to a project, without needing to aprove the hours.

6. Entered hours for this user in the timsheet and released the hours.

I asked myselve how the system knows the account determination group for the resource, as I only assigne the account determination group to the service? What else could be the problem?

Thanks a lot


Claus

former_member630407
Participant
0 Kudos

Hi Da Som Baek

Here are some of my inputs for your question and the trail conversations.

Labor Cost Assignment

The Labor Cost Rate is assigned to job assignment. In specific, Job Assignment is the Job Definition that is assigned to every employee while hiring. Every job definition can be tagged to a Cost Rate in ‘Labor Resource’.

Here, every employee performing a particular job with same job definition will have the same Cost Rate irrespective of the services they will perform.

Mostly, One service is tagged to one Labor Resource. For same resources performing different services at different cost rate, new labor resource is created.

If there are multiple set of books, different Cost Rate can be maintained for same Job Assignment.

Once you have maintained the cost rate on the Valuation tab, the system will use this cost rate. You can define the limit of the period for which the cost rate is valid using the delimit function. This enables you to enter a date until which this cost rate is valid.

The above configurations can be enabled for a particular cost center assignment in a Company. The resource usage is enabled for ‘Resource Relevant for Financials’.

When an employee with a Labor Resource Cost Rate is assigned to a Project, the cost rate is taken into consideration for financials. If the Labor Cost rate is unavailable, service cost rate is take for financials.

This type of assignment is time-based. When an employee enters an activity confirmation, the system derives the resource from the employee’s cost center and job, and automatically defaults the resource in the confirmation.

Information on the service and the time confirmed in the time sheet is sent to financials to enable costs to be determined for the labor resources consumed. The costs are calculated based on the cost rates defined in the Cost and Revenue work center.

Additional Resources on Service Cost Allocation to Production Lots can be found here:

https://help.sap.com/viewer/2754875d2d2a403f95e58a41a9c7d6de/2005/en-US/2cb9195d722d10148f059c3a7ab2...


Cost Rate of Labor Resource and Actual Cost

Once all the business processes involved are completed correctly, the actual costing can be determined based on actual costs incurred for all objects along the value chain. The calculation is based on actual cost of materials, actual cost of labor and actual overhead costs incurred for the final product and service for a specific accounting period. Following is an explanation in specific to the Resource rates calculation.

Resource Rates Calculation

In order to calculate actual cost for internal service confirmations the system collects all costs incurred by a production cost center and distributes them completely to the cost center’s resources. This is done proportionate to the cost posted for internal service confirmations in the period, meaning that these preliminary cost are used as an equivalence figure to distribute actual cost center costs to resources. Thus the planned resource cost rates can be used to ensure that expensive resources receive an appropriately higher share of the total actual cost.

Additional Resources on Actual Costing can be viewed here:

https://help.sap.com/viewer/2754875d2d2a403f95e58a41a9c7d6de/2005/en-US/2cb2b256722d101487d7a0fa9d6a...


Payroll in SAP ByD

If you would like to implement payroll processing for employees and service agents, following is the process.

SAP offers a file-based payroll process with the solution, to support integration with external payroll services providers. SAP Business ByDesign helps ensure that you retain control over and visibility into your payroll process, even when it is outsourced.

Additional Resources for SAP ByD Payroll is here

https://help.sap.com/viewer/2754875d2d2a403f95e58a41a9c7d6de/2005/en-US/2ce8a791722d1014a48eef3f503e...

Pay Wages

The process of daily or weekly wages can be carried out using automated invoice receipts which is Evaluated Receipt Settlements. This can be done using a Supplier Contract which triggers Supplier invoices on a daily or weekly basis. The Scheduling run can be defined in Supplier Invoice WC. Process Flow for ERS is as follows: 1.Schedule ERS run

In the Evaluated Receipt Settlements view of the Supplier Invoicing work center, you can specify, for example when and how often the run should be scheduled.

In each ERS run, the system creates invoices for all purchase orders that are marked for ERS. To exclude a purchase order from a scheduled ERS run, you can deselect ERS in the relevant purchase order.

2.Invoice data sent by preceding documents

The system copies the invoicing data from the purchasing documents for which the invoice is required. The system uses a purchasing contract, if involved in the process, and the purchase orders marked for ERS with one of the following purchasing documents:

§Goods and services receipt

§Confirmed inbound delivery

The system creates invoices covering the values and quantities agreed upon with the supplier.

The assignment of purchase orders to ERS is automatic when ERS is selected for that supplier. You can deselect ERS for a specific purchase order if you want to exclude that purchase order from the scheduled ERS run. The system uses the prices in the relevant purchase orders and the quantities in the relevant goods and services receipts or inbound deliveries to create and post invoices on behalf of the suppliers.

3.Invoice is verified - The system checks the supplier invoice for consistency.

4.Invoice is posted

After the invoice has been verified, the system posts the invoice.

The system notifies:

oPurchasing of the values and quantities of an invoice that refers to:

§Purchasing contract

§Purchase order with a limit item from a purchasing contract for which there is no goods receipt

oAccounting-relevant data

oPayments and taxes that are due

oPayments to a non-resident supplier, where relevant

Tax on materials and services occurs in purchasing transactions like purchase orders and supplier invoicing. Tax abroad is applicable when your company needs to apply foreign taxes. In purchasing, it is possible to receive a supplier invoice with foreign tax even if the company is not registered with the foreign tax authority. The system automatically determines the applicable tax in the supplier invoicing process.

Before forwarding the data to Financials, the system checks whether the relevant accounting period in Financials is open. If the accounting period is closed, the system issues an error message or a warning message.

5.Supplier is notified

Depending on the invoice format in which the supplier is to be notified, the system sends one of the following messages to the supplier's external invoicing system:

oERS invoice using SAP Electronic Data Exchange (EDX), sent in XML format

oERS invoice form sent as an e-mail with the ERS invoice attached in read-only form

The ERS invoice can also be sent by mail or by fax to the supplier.

If an ERS invoice is canceled, the supplier is also notified about the invoice cancellation.

6.Supplier creates customer invoice in external system

The supplier receives the supplier invoice created by ERS and creates a customer invoice based on the received data.

For Additional Resources on Evaluated Receipt Settlement, please verify:

https://help.sap.com/viewer/2754875d2d2a403f95e58a41a9c7d6de/2005/en-US/2de2ef3b722d10149e148b2bd00c...

https://answers.sap.com/questions/408593/ers-invoices--sap-bydesign.html

https://answers.sap.com/questions/558742/purchase-invoice-for-service-agent.html

Hope this could solve most of your queries.

edayang
Advisor
Advisor
0 Kudos
former_member627545
Participant
0 Kudos

Hi Eda,

Thank u for the answer. But, unfortunately, it may be explaination of internal project for business development and enhancement ...

I think direct cost distribution rule is following :

1. Estimate cost : When i just estimate product cost, i can use cost rate of labor resource or service for a work.

2. Actual cost : I think actual payroll data lead actual direct labor cost into product. So, i guess i need payroll data to get the actual labor cost.

Is there any error? What do you think Eda?

I'll really appreciate you if you and your team provide some solution

Regards,
Dasom