Hello all,

I have an order of 13000 pc,

2 work centres,

  • Work centre A with 14 individual capacities (only cotton shirts);
  • Work centre B with 8 individual capacities(cotton and wool shirts);

My order is to produce cotton shirts.

My order makes the work centre A full so I need to put the rest of the pcs in the work centre B because this work centre is also available to produce cotton shirts.

But how can I say this in SAP? How can I say that an order is going to "share" two work centres"?

Hope you can help.

Thank you.

Regards,

Jose

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Nov 10, 2019 at 01:21 PM

    Hello

    The standard capacity leveling transactions will not split your operation between two work centers.

    What you can do in Capacity Leveling is to let system automatically select a new production version in case of an overload in the work center, by setting the flag "change production version on error" in your strategy profile. However, with this setting you will dispatch the whole operation to a new work center and there will be no split.

    Regards,
    Caetano

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.