Information message Date adjust. level incorrect: Plant XXXX/ord.type PE / prod.sched in MF50

former_member254501
Active Participant
0 Kudos

Hi All,

on MF50 initial screen getting message like Date adjust. level incorrect: Plant XXXX /ord.type PE / prod.sched,

I have maintained OPU5 setting also maintained proper prod version and scheduling parameter in input parameter of MF50.

Finite capacity is ticked in workcenter, shifts are also maintained.

In dev not getting this message but in quality it is there what setting I am missing.please guide

Regards

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Please compare setting of OS80 and OSP1 in quality and development system,

Also check OPU5 setting for adjust date too.

For message REMPT301 please refer this old discussion

Problem in REM Planning table and SAP consulting note 178525 - MF50: Explanation --> scheduling

Best Regards,

R.Brahmankar

former_member254501
Active Participant
0 Kudos

Hi Thanks for quick response I did checked OS80,OSP1,and OPU5 when checked dev for one plant it is working for one plant it is gicing message both have same OPU5 setting as below also refered old blog but still couldnt figure out whats the issue

rupesh_brahmankar3
Active Contributor

Hello,

Issue is here in adjust dates

Best Regards,

R.Brahmankar

Answers (0)