Skip to Content
0
Nov 04, 2019 at 11:01 AM

SNC smi RO does not consider the latest GR processing time

55 Views

Background:

The SNC "min/max monitor" and "SMI monitor" shows the Replenishment orders in availability date bucket (Delivery date + GR processing time).

Issue:

When a products GR processing time is changed all the existing orders remains in the old GR processing time. There are around 1200+ existing ROs which shows incorrect GR processing time after the master data is changed. We cannot ask the supplier to change the ROs to have the latest GR processing time reflected.

Is there a program in SNC that can mass re-read master data and move the orders in Min/Max monitor according the new GR processing time?

thanks