Skip to Content

REM- Reduction in planned order quantity after the scrap confimation

HI,

I have requirement, where user want planned order quantity depletion in MRP after the Assembly Scrap confirmation in MFBF Tcode.

Example scenario: I have planned order of 100 Qty, and i have performed the assembly scrap confirmation for the 10 Qty.

then in Next MRP Run the planned order qty should be 90.

Thanks in advance.

Venkatesh

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Nov 05, 2019 at 07:19 AM

    Hello,

    Once you do the MFBF planned order gets firmed which will not be deleted by MRP.

    So you need to have unfirm planned order so that MRP will delete it and create with required quanity.

    Go to REM profile's setting OSP2 From "Control data 2" select "do not firm" indicator. So planned order will be unfirmed and MRP will delete and recreate it.

    Please refer SAP KBA 1901138 - Firmed planned order cannot be deleted after MRP run

    Best Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

    • Hello,

      When you post the scrap does system posted 131 movement? Check the material document which posted as scrap.

      Assembly scrap at MFBF no movement type 131 only components are posted with movement type 261. So it would not reduce the planned order.

      For more details please refer SAP KBA - 2029238 - Scrap component at MFBF

      Best Regards,

      R.Brahmankar

  • Posted on Nov 05, 2019 at 11:44 AM

    Hi Venkatesh,

    In MFBF irrespective of any posting (Assembly back flush /Reporting point confirmation) Planned order will be automatically firmed.Before running MRP make sure that firmed planned order are deleted/ unfirmed. SInce MRP will not delete the firmed planned order.

    Regards

    Prasath E

    Add a comment
    10|10000 characters needed characters exceeded