SAP B1 - Production Order Closing Entry

Dear

The production order has the following status.

Planning Quantity = 10

Completed Quanity = 4

Actual Item Component Cost : INR 99,797.50

Actual Product Cost : INR 39,508.59

Total Variance : INR -60,288.91

After closing the production order in SAP B1, we get the following JV posting.

1) WIP VARIANCE debit 60,288.91

2)WIP INVENTORY credit 60,288.91

3) WIP VARIANCE credit 60,288.91

4) Finish Good Inventory Debit 60,288.91

Why the wip varaince account is credited and Finish Good Inventory account is debited by variance amount 60288.91 (line 3 and 4)?

Regards

Narendra

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • Posted on Nov 05, 2019 at 08:07 AM

    You have issued INR 99.797,50 worth of components and received only INR 39.508,59 worth of finished products. When closing production order the value of finished goods will be increased or decreased by variance amount so that it is equal to the value of issued components (assuming that valuation method for product is not Standard).

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.