Hi,
Planner Has activated Processing Indicator OFF in MD06 for a material, when MRP background job executed and it re activated the Processing Indicator with status ON. I have checked, there is no changes to material. if there is no MRP relevant changes why MRP again activated the processing Indicator. please share your inputs.
Hello,
The processing indicator changes back to the initial state when the material is planned by MRP and a new MRP list is generated.
The MRP list is updated after you ran MRP. Which reset the processing indicator as you have exception message. The processing indicator for the MRP lists (Transaction MD05) is not deleted during planning if no new exceptions exist.
Please refer SAP consulting note 30684 - Exception adjustment in the planning run
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Did you read SAP note e 30684 - Exception adjustment in the planning run?
If there are exception messages in the MRP list that was just created, the system searches for matching exceptions in the old MRP list that is indicated as processed.
If the corresponding exception is then found, it is characterized in the new list as 'old'. If this applies to all the exceptions of the new list, the processing indicator of the MRP list is retained.
Best Regards,
R.Brahmankar
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.