Hello Experts,

I have done standard configuration for progress analysis in SAP PS. But cost element are not created with category 61.Is it still possible to get progress analysis in CNE5 report

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Oct 30, 2019 at 10:46 AM

    Cost element are needed for storing the progress results i.e. POC. Hence please it is needed to maintain the same.

    In case not maintained, there are chance of not showing any output.

    regards,

    Pradeep

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 30, 2019 at 11:11 AM

    Hi Pradeep,

    Do you know any workaround solution provided by SAP

    Regards,

    Ronak Parikh

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.