MRP delivery date to be blocked while creating PO

how to make not editable of delivery date while creating PO for MRP material but we have to change delivery date for manual PR(me51n)

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Posted on Oct 31, 2019 at 02:12 AM

    You can using BAdI ME_PROCESS_PO_CUST method FIELDSELECTION_ITEM for arrange when delivery date field can change or not.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Oct 31, 2019 at 10:28 AM

    Hello

    As per standard SAP the field selection is the only way to handle the fields behavior. We can make it editable/non editable/ mandatory.

    In your case you can create a separate document type for manual PR and create a Z field selection key copy of NBB and assign the Z field selection to Z PR document type and in Z field selection key go to field selection group Deadline monitoring and make the Delivery date as required. And make it display for MRP relevant document type.

    If this solution doesn't suits your requirement, then enhancement is the only option. Use BADI ME_PROCESS_REQ_CUST BADI and ask developer to code your requirement.

    Thanks

    Harman

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.